RC Infrastructure

Case study / Civils

Scotland electrification: enabling civils.

Piled foundations, access roads and troughing on a major Scottish electrification route. Sequenced to the wiring programme and handed over on each possession boundary.

Aerial view of a construction compound, haul road and new bridge abutments beside a two-track electrified railway running through farmland.
Fig. 6.1Enabling works beside an electrified main line: a construction compound and new structures laid out around the railway.
Value band
£14m
Duration
2.5 years
Status
On site

01Summary

Client, value and status at a glance.

Client
Network Rail Scotland (via prime)
Capability
Civils
Region
Scotland
Value band
£14m
Duration
2.5 years
Status
On site

02The work

What it took, and where it stands.

  1. The challenge

    Civils that set the pace for the wiring behind them.

    On an electrification route, every foundation, access point and troughing run has to be ready before the wiring teams arrive. A late handover costs a possession.

  2. What we are delivering

    Foundations, access and troughing, sequenced to the wiring.

    Piled foundations for the overhead line structures, access roads and cable troughing routes, planned against the wiring programme and handed over at each possession boundary.

  3. Where it stands

    On site now.

    Works are in progress, with completed sections handed to the wiring programme as each possession closes.

Next step

Delivering a similar scheme? Talk to the team behind this one.

References and full project documentation are available on PQQ or tender request.