RC Infrastructure

Capability 01 / Rail electrification

From first survey to first service.

We design, install, test and commission overhead line equipment for mainline, metro and private rail networks across the UK. In possession, on programme, handed back ready for service.

System heightContact wire heightRail levelStaggerCatenary wireCantileverRegistration armContact wireMastFoundationTrack centre linePantograph25 kV AC
Overhead line: cross-sectionRCI-03-AIndicative arrangement. Not to scale. Drag sideways to pan.
Design stages
GRIP 1 to 4
Mainline voltage
25 kV AC
Catenary systems
Series 1, 2, Mk3B

01What we deliver

Self-delivered, end to end.

No stitched-together supply chain. No accountability gaps at discipline boundaries.

  1. 01GRIP 1 to 4 design and detailed design
  2. 02Catenary systems: Series 1, Series 2, Mk3B and bespoke
  3. 03Masts, portals, small part steelwork, registration and wiring
  4. 04Isolation and possession support
  5. 05Testing and commissioning to Network Rail and ENA standards
  6. 06Entry into service and defect close-out
  7. 07Post-handover maintenance for private networks
  8. 08Interface with signalling, permanent way and civils
Crews in orange hi-vis building a station platform beneath new overhead line gantries, with a second crew in a raised access platform at the overhead line equipment and a passenger train approaching on the adjacent line.
Fig. 3.1Platform works, an overhead line crew and a running railway in one frame.

02Four phases, one schedule

Design. Install. Test. Maintain.

Every electrification scheme we take on is broken into four phases, delivered by one team on one Gantt.

Client-accepted
Network Rail
RIDDOR, rolling 365 days
0
Longest package
4 years
  1. 01Design

    Interface clashes are resolved on paper, not on the rail head.

    Our in-house designers work from GRIP 1 through to AFC issue. We interface early with signalling, telecoms, permanent way and civils, so that clashes are found on the drawing and not during a possession.

    Two engineers in orange hi-vis study a set of drawings while standing on newly laid switches and crossings, with track crews and a city skyline behind.
    Fig. 3.2Drawings checked against newly laid switches and crossings: the permanent way interface an overhead line design has to agree with.
  2. 02Install

    Led by engineers who came up through the corridor.

    Self-delivered crews plan possessions to the hour and sequence civils and OLE on one Gantt. Contingency is built in, so that trains still run at 04:58 even when the weather does not cooperate.

    Two linesmen in the raised basket of a road-rail access platform beneath a new overhead line gantry, with a colleague on the track below.
    Fig. 3.3Linesmen work at a new gantry from a road-rail access platform during a possession.
  3. 03Test and commission

    Audit-ready on the first submission.

    Our test engineers run site acceptance to a standard that clears Network Rail or infrastructure manager audit on the first pass. Commissioning packs are issued ready for entry into service, without chase cycles.

    A two-track electrified railway seen from an overbridge, with new galvanised masts and cantilevers carrying the overhead wires into the distance.
    Fig. 3.4Foundations, masts, cantilevers and wires: the finished sequence on a two-track main line.
  4. 04Maintain

    Long-term asset stewardship for private networks.

    For private networks and depot electrification, we provide planned maintenance, fault response and long-term asset stewardship. Same engineers, extended relationship.

    Track workers in orange hi-vis walking along an electrified railway beneath the overhead wires, with a road-rail machine and a signal in the distance.
    Fig. 3.5Walking the line under the wires.

03Typical scheme

The shape of a rail scheme we would take on.

Route length
2 km to 80 km per delivery package
Duration
6 months to 4 years
Team size
8 to 60, depending on possession window
Value band
£1m to £40m+ per package
Voltage
25 kV AC on the main line, DC on metro and light rail
Settings
Mainline, metro, light rail, depots and sidings

Accredited

  • RISQS
  • Link-up
  • ISO 9001
  • ISO 14001
  • ISO 45001
  • Constructionline
  • CHAS
  • Achilles UVDB

Next step

Starting an electrification scheme? Bring us in early.

Framework enquiries, scope reviews, design-assist and PQQ support. First response within one working day.