RC Infrastructure

Case study / Power & HV

Renewable generation grid connection.

Pre-application route review, detailed design, build and commissioning for a 132 kV import and export grid connection supporting a generation scheme.

Aerial view of a battery energy storage site: rows of green battery containers, a fenced substation compound and transmission towers beyond.
Fig. 6.1A substation compound and transmission towers, seen across the battery containers of an energy storage site.
Value band
£9m
Duration
14 months
Status
Delivered

01Summary

Client, value and status at a glance.

Client
Renewables developer
Capability
Power & HV
Region
North
Value band
£9m
Duration
14 months
Status
Delivered

02The work

What it took, and how it ended.

  1. The challenge

    A connection that had to satisfy the network operator before it could energise.

    A 132 kV import and export connection depends on the route, the point of connection and the network operator’s requirements being settled early. Each of them can move the energisation date.

  2. What we delivered

    From route review to commissioning.

    Pre-application route review, detailed design, construction and commissioning of the 132 kV connection, with network operator liaison handled by the same team throughout.

  3. Outcome

    Built and commissioned as one package.

    The connection was designed, built and commissioned by one team, from the first route review through to energisation.

Next step

Delivering a similar scheme? Talk to the team behind this one.

References and full project documentation are available on PQQ or tender request.